by Macaulay Hey | Sep 4, 2016 | |
Lihir Kapit PFS - Capital Cost Estimate 3 Project Description: The +$1.5B CAPEX Project included: Sheet-pile cut off wall across the face of the bay and subsequent dewatering Excavation of 1 Mm3 unsuitable, depressurisation and construction of an earth and rock...
by Macaulay Hey | Sep 4, 2016 | |
Surat Basin Rail - Procurement 3 Project Description: Flagstaff was engaged to work as part of an integrated owner’s team to execute the procurement phase of the project. The procurement model adopted was a duel Early Contractor Involvement (dECI). The engagement...
by Macaulay Hey | Aug 23, 2016 | |
BHP Olympic Dam Expansion Study - Capital Cost Estimate 3 Project Description: AECOM were awarded the infrastructure package for the Selection Phase Study in relation to the Olympic Dam Expansion (ODX). The infrastructure package addressed the transportation of...
by Macaulay Hey | Aug 23, 2016 | |
Madagascar Alumina - Feasibility Study Estimate 3 Project Description: Conceive project for bauxite mine and alumina refinery in Southern Eastern Madagascar: Develop bauxite haulage concepts – road and rail Mine infrastructure Alumina refinery sites Export...
by Macaulay Hey | Aug 23, 2016 | |
Alumina Refinery Guinea - Capital Cost Estimate 3 Project Description: Concept level study for red side of proposed alumina refinery, Kamsar, Guinea Identify module construction locations (PAM yards) around the world Take modular design from previous project and...