Project Description:

Berth 2

  • Replacement of 3 remaining fenders
  • Replace capstan winches
  • Replace walkway
  • Access improvements on ship loader
  • Replace berth amenities building

Berth 1

  • Replacement of 6 fenders
  • Replacement of capstan winches
  • Ship loader modifications

Project Details

Client: BHP Billiton Mitsubishi Alliance

The Challenge:

  • Both projects conducted as shutdowns with fixed operational restart time
  • Available window fixed to meet export commitments
  • Berth 2 shutdown required co-ordination of multiple contractors

The Outcome:

N

Engaged with site project delivery group to develop the schedule

N

Reviewed contractor schedules and worked with the contractors to establish resourced schedules to allow earned value monitoring through the shutdown

N

Assessed status daily and produced daily reports based on earned value

N

Provided daily report inputs for the BMA Project Manager’s report

N

Identified schedule risks in the contractor progress and proactively worked with the contractor and BMA with recommendations to ensure berth was operational by the required milestone

N

For both shutdowns the facilities were available by the nominated time

Want more information about this project?

Contact the project leader for more information, or alternatively download the project data sheet.
Contact JohnView Project Data Sheet
Melbourne Office:
Suite 65, 3 Albert Coates Lane
Melbourne Victoria 3000
Australia

Telephone: (03) 8679 2284

Brisbane Office:
Level 6, 87 Wickham Terrace
Spring Hill Queensland 4000
Australia

Telephone: (07) 3831 2811
Facsimile: (07) 3839 5370